Camping World Stadium Renovation: $400 Million Upgrade and Expansion
On February 24, 2025, the Orlando City Council approved the selection of the joint venture between Barton Malow and AECOM Hunt as the primary contractor for the renovation of Camping World Stadium. Valued at approximately $400 million, the project aims to enhance the stadium’s facilities. This will enable it to better accommodate future sports and cultural events.
Project Details:
- They will install an additional 2,000 seats, increasing the total capacity from 63,000 to 65,000 spectators.
- They will remove the existing upper grandstands on the eastern and western sides and replace them with new, integrated seating, improving the spectator experience.
- They will construct a 100,000-square-foot indoor event center within the stadium complex, which will expand the types of events they can host and integrate the renovation plans for Camping World Stadium.
- Additional Enhancements: Upgrades will include modernised sound and lighting systems, improved concourses, and restroom facilities. The creation of exclusive fan zones is aimed at enriching the overall attendee experience as part of the Camping World Stadium renovation.
Timeline and Impact:
- Expected Completion: The renovation is slated for completion by late summer 2027. This will ensure the stadium is ready for major events thereafter.
- Event Hosting: Orlando plans to host temporary home games for the Jacksonville Jaguars during the 2027 season. This is due to concurrent renovations at their home stadium.
Project Funding:
- They will finance the renovation through revenues from the 6% Tourism Development Tax (TDT), which is levied on hotel stays and short-term rentals in Orange County. This funding approach reflects the region’s growing tourism sector and supports the Camping World Stadium renovation.
This renovation represents a significant investment in Orlando’s infrastructure. It aims to enhance the city’s capacity to host a wide range of major events in the future.
Project Summary:
Element | Details |
---|---|
Project Value | $400 million |
Seating Capacity | Increase by 2,000 seats (from 63,000 to 65,000) |
Grandstand Upgrades | Replacement of upper grandstands with integrated seating |
Multipurpose Center | Construction of a 100,000-square-foot indoor event space |
Enhancements | Upgrades to sound and lighting systems, concourses, restrooms, and creation of fan zones |
Completion Date | Late summer 2027 |
Funding Source | Tourism Development Tax (TDT) |