Landlord and Tenant Fit-Out: The Delivery Boundary and Who Builds What

Fit-out is the work that turns a building’s base construction into usable, occupied space. Between the structure a developer delivers and the environment an occupier finally works in lies a boundary: a line that separates what the landlord builds from what the tenant builds, what the landlord maintains from what the tenant maintains, and what must be removed when the lease ends. This boundary is rarely a single physical plane. It is a negotiated distribution of fit-out responsibility across the structure, the services, the finishes and time. Where it is drawn determines cost, programme, risk and the quality of the finished interior. This article describes how that responsibility is divided in commercial leasing, the vocabulary used to describe delivery conditions in different markets, and the contractual instruments that govern changes and their eventual removal.
Delivery conditions: from shell and core to a finished base build
The lowest level of completion commonly handed over is shell and core. In this condition the landlord has completed the primary structure, the external envelope (cladding, roof and windows) and the building core — lifts, staircases, primary risers and the main plant and incoming services — while the lettable floors are left as bare, serviced space. Capped services are brought to the floor, but there are no ceilings, raised floors, internal finishes or terminal mechanical and electrical installations (Designing Buildings, 2024). Shell and core lets a developer market and let space before occupiers are known, and lets each occupier complete the interior to its own requirement.
Category A, Category A+, and Category B
In United Kingdom office practice the fit-out beyond shell and core is described in categories associated with the British Council for Offices (BCO) Guide to Specification. A Category A fit-out brings the landlord’s space to a consistent, lettable standard: raised access floors and suspended ceilings, basic internal surface finishes, distribution of mechanical and electrical services including heating, ventilation and air conditioning, lighting, fire detection and sprinklers, and finished common parts (Designing Buildings, 2024; Morgan Lovell, 2024). A Category A floor is complete but generic — it is not yet anyone’s office.
Category B is the occupier’s fit-out: the installation that makes the space specific to one organisation. It includes partitioning and room layouts, meeting and focus rooms, reception and branding, specialist lighting and finishes, floor and wall coverings, furniture, and information-technology and audiovisual infrastructure (Peldon Rose, 2024). An intermediate condition, Category A+ (also called ‘plug and play’), has emerged in which the landlord delivers a near-complete, furnished suite — kitchenette, meeting rooms and furniture — so a small occupier can move in without commissioning its own Category B works (Crown Interiors, 2024).
Shell variants and the allowance model
Other markets use different language for the same underlying question: how complete is the landlord’s delivery? In United States commercial practice, a cold shell is an unconditioned, unfinished space without distributed air conditioning, ceilings or interior build-out; a warm shell adds conditioned air, basic electrical service and sometimes restrooms; and a vanilla shell (or ‘vanilla box’) is finished to a neutral, ready-to-occupy baseline with walls, flooring, lighting and climate control (LoopNet, 2023). Rather than naming categories, United States leases frequently quantify the landlord’s contribution as a tenant improvement allowance — a sum, often expressed per square foot, that the landlord contributes toward the occupier’s interior works, with costs above the allowance borne by the tenant (Cushman & Wakefield, 2023). The allowance model and the category model are two ways of expressing the same boundary: how much of the finished interior the landlord pays for and builds, and how much the occupier does.
Services at the boundary
Mechanical, electrical and plumbing services cross the delivery boundary in a way that finishes do not, and this is where most coordination failures occur. In a Category A delivery the landlord typically installs primary distribution — air handling to the floor, a lighting grid, a fire system — designed for an assumed, open-plan occupancy. The occupier’s Category B works then subdivide the floor, which changes the loads the base services were sized for: partitions interrupt air paths, meeting rooms concentrate occupancy and heat gain, and server or equipment rooms impose cooling and power demands the base build did not anticipate. The boundary question is therefore not only ‘who installs the duct’ but ‘whose system is relied upon, and who is responsible when the subdivided layout defeats the base design’. Clear documentation of base-build capacities, and early sharing of the occupier’s layout, is what keeps the two scopes compatible. The distinction matters most where it meets the way a building is measured and let, a subject treated separately in net, gross and rentable floor area.
Consent, alterations and coordination
Because the occupier’s works alter a building the landlord owns, they are controlled. In leasehold practice, non-structural internal alterations are usually permitted with the landlord’s consent, formalised in a licence for alterations (also ‘licence to alter’) — a separate agreement recording the approved works, the conditions attached, and any obligations at lease end (RICS, 2021). The licence protects the landlord’s asset and the building’s warranties, and protects the tenant by fixing what has been agreed in writing. Coordination across the boundary — between the landlord’s base-build team, the occupier’s fit-out contractor and the building’s ongoing operation — is a defined management task, not an incidental one, particularly in multi-tenant buildings where one occupier’s works affect shared risers, cores and systems. Fitting out while a building remains partly occupied adds a further layer of disruption and sequencing, as discussed in uncertainty in occupied building renovation.
Reinstatement and the end of the lease
The boundary reappears at the end of the lease. Many leases require the tenant to remove its alterations and return the space to an earlier condition — commonly the Category A standard recorded in the licence — an obligation known as reinstatement and assessed within the wider law of dilapidations (RICS, 2023). What must be removed, and to what standard, is governed by the lease and the licence rather than by preference, and disputes are common where the documented condition is unclear (Better Buildings Partnership, 2019). Reinstatement carries a sustainability cost that is increasingly questioned: stripping serviceable partitions, ceilings and finishes to return a floor to a generic state, only for the next occupier to install comparable elements, generates avoidable waste. Some landlords and occupiers now negotiate to retain rather than remove usable fit-out.
Limitations
The categories and shell descriptions here are market conventions, not universal legal definitions; the precise contents of a ‘Category A’ delivery or a ‘warm shell’ vary between buildings, specifications and jurisdictions, and the governing document in any transaction is the lease and its licences, not a general category name. The United Kingdom category system and the United States shell-and-allowance language describe overlapping but not identical practices, and neither maps cleanly onto every national market. This article does not address the valuation, taxation or accounting treatment of fit-out and allowances, which are significant and jurisdiction-specific, nor the detailed fire, accessibility and building-control approvals that any fit-out must satisfy.
ArchUp reading
The value of the fit-out boundary is that it lets buildings be let before occupiers exist, and lets interiors be specific without rebuilding the base. Its weakness is that a boundary optimised for lettability — a generic Category A floor, a per-square-foot allowance — can push cost and carbon onto the occupier and onto the end of the lease, where reinstatement quietly undoes recent work. The point is a measured one: the delivery condition is a design decision, not a neutral starting line. Where the boundary is drawn, how clearly the base-build capacities are documented, and whether reinstatement is required or waived shape a building’s cost and its waste as much as any visible design move. Reading a fit-out well means reading the lease and the licence alongside the plan.
References
British Council for Offices (BCO). BCO Guide to Specification. London: BCO.
Designing Buildings Wiki (2024). Category A fit-out works and Fit out of buildings. Available at: designingbuildings.co.uk.
Morgan Lovell (2024). The difference between Cat A and Cat B fit out.
Peldon Rose (2024). The difference between Cat A, Cat B and Cat C office fit out.
Crown Interiors (2024). Shell and Core, Cat A, Cat A+ / Plug and Play, and Cat B fit out.
LoopNet (2023). Understanding Existing Office Space Conditions.
Cushman & Wakefield (2023). Tenant Improvement Allowance.
RICS (2021). How to process licences to alter. RICS Built Environment Journal.
RICS (2023). Dilapidations in England and Wales, 7th edition, RICS professional standard. London: Royal Institution of Chartered Surveyors. ISBN relates to the published standard.
Better Buildings Partnership (2019). Guidance Note 10.2: Alterations and dilapidations.